Stages Of Work
Week 1 – Preliminaries & Strip-Out

  • Site possession and setup (hoarding, welfare facilities, access control)
  • Strip-out of existing finishes and fixtures
  • Site surveys (electrical, mechanical, structural, if needed)
  • Final confirmation of design details with contractors
Week 2 – Base Build & First Fix

  • First fix of Mechanical, Electrical & Plumbing (MEP)
  • Cable routing and containment
  • Partition framing (plasterboard or glass walls)
  • Floor preparation (screeding, leveling)
Week 3 – Finishes

  • Painting and decorating
  • Ceiling installation and lighting
  • Flooring works (carpet, vinyl, tiles)
  • Second fix MEP (switches, sockets, plumbing)
Week 4 – Furniture, Testing & Handover

  • Installation of furniture and equipment
  • Blinds, signage, and final decorative touches
  • Testing and commissioning (fire alarm, MEP)
  • Snagging, cleaning, client walkthrough, handover pack